Types EZH and EZHSO
15
Wide-Open Monitor Regulator
1. Follow the procedures in the All Installations section,
and then continue with step 2 of this section. The
sense and bleed control lines of both the upstream and
downstream pilots will be connected to the downstream
piping (see Figure 13).
2. Connect the pilot supply line for the downstream
regulator to the outlet "R" port of the Type SA/2 pilot
supply lter regulator.
Working Monitor Regulator
1. Follow the procedure in the All Installations section, and
then continue with step 2 of this section. The sense line
of the upstream monitor pilot and the bleed and sense
lines of the downstream pilot will be connected to the
downstream piping (see Figure 14).
2. Connect an inlet supply line from the upstream piping
to the inlet "M" port of the downstream Type SA/2 pilot
supply lter regulator.
3. Connect a control (sense) line from the "A" port of the
upstream working Type PRX pilot to the intermediate
pressure portion of piping, using 8/10 (inside diameter) tube.
4. Connect a downstream bleed line from the "S"
port of the upstream working Type PRX pilot to the
intermediate pressure portion of piping, using 8/10
(inside diameter) tube.
STARTUP AND ADJUSTMENT
Pre-startup Considerations
Each regulator is factory-set for the outlet pressure specied
on the order. If no setting was specied, outlet pressure
was factory-set at the mid-range of the pilot control spring.
Before beginning the start-up procedure in this section make
sure the following conditions are in effect:
• Block valves isolate the regulator
• Vent vales are closed
• A bypass, if any, is in operation.
In all cases, check the control spring setting to make sure it
is correct for the application.
CAUTION
Be sure to slowly introduce pressure into the
system to prevent downstream overpressure
due to potential rapid pressure increase.
Pressure gauges should always be used to
monitor downstream pressure during startup.
Procedures used in putting this regulator
into operation must be planned accordingly
if the downstream system is pressurized by
another regulator or by a manual bypass.
TYPE EZH OS2 SLAM-SHUT VERSION
In the case of opening the mechanism box lid:
1.
After arming, never leave the key on the stem
2. Never put your ngers in or near the
reset mechanism area
Note
When using a Type SA/2 pilot supply lter
regulator, the differential pressure across the
regulator must be at least 3 bar for optimum
regulator performance. The Type SA/2 can
be removed if differential pressure across the
regulator is less than 3 bar and inlet pressure
stays at or below 13.8 bar.
Startup
Type EZH Startup:
1. Make sure all block valves, vent valves, and control line
valve(s) are closed.
2. Back out the pilot adjusting screw(s).
3. Slowly open the valves in the following order:
- Inlet block valves.
- Pilot supply and control line valve(s), if used.
4. Crack open the outlet block valve or bypass valve to
allow minimum ow.
5. After adjusting the Type PRX pilot(s) to the desired
pressure setting(s), slowly open the downstream block
valve wide open.
6. Close the bypass valve, if used.
Type EZHSO Startup:
1. Make sure all block valves, except valve R4, vent
valves, and control line valve(s) are closed.
2. Back out the pilot adjusting screw(s).
3. Introduce upstream pressure by slowly opening inlet valve.
4. Slowly open valve R2.
5. Open valve R3.
6. Close valve R4, the regulator Type EZHSO close.
7. Open valve R4.
8. Close valve R3.
9. Slowly open downstream valve, making sure that
there is a constant sufcient pressure drop across the
regulator. If downstream pressure climbs too close to
upstream pressure, the regulator will again fully open.
In this case, start-up procedure needs to be repeated.