Reference Manual
00809-0100-4801, Rev FA
October 2010
Rosemount 3051S Series
2-28
3. Open the equalize valve on the low pressure
(downstream) side of the transmitter. The manifold
is now in the proper configuration for zeroing the
transmitter.
Test
(Plugged)
Test
(Plugged)
Equalize
(open)
Process
Isolate
(closed)
Isolate
(open)
H
L
Process
Equalize
(open)
Drain Vent
(closed)
Test
(Plugged)
Test
(Plugged)
Equalize
(closed)
Process
Isolate
(closed)
Isolate
(open)
H
L
4. After zeroing the transmitter, close the equalize
valve on the low pressure (downstream) side of
the transmitter.
Process
Equalize
(open)
Drain Vent
(closed)
5. Close the equalize valve on the high pressure
(upstream) side.
Test
(Plugged)
Test
(Plugged)
Equalize
(closed)
Process
Isolate
(closed)
Isolate
(open)
H
L
Process
Equalize
(closed)
Drain Vent
(closed)
6. Finally, to return the transmitter to service, open
the low side isolation valve.
Test
(Plugged)
Test
(Plugged)
Equalize
(closed)
Process
Isolate
(open)
Isolate
(open)
H
L
Process
Equalize
(closed)
Drain Vent
(closed)